WESTERN DUBUQUE BIODIESEL
FARLEY, IOWA

SOY BIODIESEL PRODUCTION FACILITY
- Contractor/Engineer: Todd & Sargent, Inc., Ames, Iowa
- Client Data: Western Dubuque Biodiesel is a LLC group located in central Iowa.
- Summary of Project Features:
- 30 million gallon per year Soy Biodiesel Facility.
 
- Storage Bins
- 2 - 500,000 gallon crude oil tanks.
- 3 - 500,000 gallon biodiesel tanks.
- 2 - Glycerine tanks.
- 2 - Refined oil tanks.
- 1 - Soapstock tank.
- 1 - Fatty acid tank.
 
- Capacity is based on running 24 hours a day, 7 days a week, 330 days a year.
 
- Support Systems
- Complete plant automation, electrical and mechanical installation.
- Precast concrete control and utility core.
- Pre-engineered metal support and receiving buildings.
 
|