PARRISH & HEIMBECKER, LTD
TISDALE, SASKATCHEWAN

INLINE GRAIN TERMINAL
- Contractor/Engineer: Todd & Sargent, Inc., Canada, LTD
- Summary of Project Features:
- Slipformed Concrete Elevator:
- 340,000 bushels of storage in 20 bins with slickcoat hoppers.
- Transfer and Distribution System rated at 15,000 BPH to elevator and existing flat storage.
- Reclaim from existing flat storage rated at 15,000 BPH.
- Jump Leg and Distribution System rated at 5,000 BPH for existing steel bins.
 
- Receiving & Shipping Systems:
- Truck Receiving rated at 15,000 BPH with 10' x 110' "dump-thru" truck scale incorporating a 6' x 54' dump grate.
- Truck loadout and audit recirculation spout rated at 15,000 BPH.
- Two-track rail loadout rated at 30,000 BPH.
- 30,000 BPH Shipping Bulk Weigher with 50 tonne upper garner.
- 30,000 BPH Sampling System.
- Railcar Reclaim System rated at 5,000 BPH.
 
- Auxiliary Systems
- Facility and Cleaner Dust Systems with 3,000 CF dust loadout bin.
- Erect PEMB for Receiving, Control, and MCC Building; Cleaning Enclosure; and Rail Loadout Booth.
- 500# capacity manlift to access bulk weigher area and bin deck.
- Considerations for future Dryer System.
 
|