P&H - Inland Grain Terminal Upgrades (Quill Lake, SK)

« View all projects

Project Description

Summary of Project Features

  • Demolition, Retrofit and New Equipment Installation
    • Remove existing relcaim equipment, top transfer drag and distributor, supports, spouting and bridge.
    • Extend receiving and shipping bucket elevator.
    • Install two (2) new gate valves and a lined u-trough to existing bulkweigher.
    • Two (2) new 12,000 BPH transfer drag conveyors from each leg to the new dual inlet distributor.
    • Install a new "Schlagel" dual inlet, 24-duct, electric distributor.
    • Install new 24,000 BPH reclaim drag and retrofit gate valves to both legs.
    • Install new dust collection baghouse and support structural.
  • Structural Supports & Access, Miscellaneous
    • Install a new structural support bent and top transfer drag bridge.
    • Install new access to the receiving leg and shipping leg extensions.
    • Install a new electric 500# capacity manlift and steel shaftway.

Project Name: 
Inland Grain Terminal Upgrades

Client Name: 
Parrish & Heimbecker LTD
Industry: 
Grain
Location: 
Quill Lake, SK